Single custom report for combined filters in MSP 2007

S

Satya

Hi,
Can I create single custom report for by combining multiple filters.
for eg., I want to create single report / view / table with the following
existing filters available in MSP 2007

Incomplete Tasks
In Progress Tasks
Critical

Regds
Satya
 
R

Rob Schneider

Satya,

Create your own filter with Menu: Project/Filtered For/More Filters ...
Press the "New" button to get the Filter Definition which should be
self-explanatory. Press the "help" button to get more guidance.

You want something like
"Critical" = "Yes" (to get critical tasks)
and
0 < "% Complete" < 100% (to get in-progress tasks, e.g. have some progress)
 
J

Jim Aksel

As an alternative, we use a filter where "Critical=yes" and "Finish>Statuse
Date" ... you should never have completed work after the status date... so
this filter gives you the remaining critical path. Rarely do we care about
what is behind us.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 
A

Andrew Lavinsky

You would need to create a new filter using the elements of those existing
filters.

Project > Filter > More Filters.....select the old ones, and note their logic,
then include that in a new one....

-A
 