Single Project Resource Usage View

M

Matt Steele

I know someone posted the answer long ago but I can't find
it now.

I want to know how to modify the filter and grouping for a
project so that the resource usage view shows only the
work totals for that one project.

I appreciate any help!
Matt Steele
 
L

Larry N

Matt - Could you please reference that posting more specifically? Maybe with
the date of posting or something. I'm having trouble finding it and would
like to know the way to accomplish the same thing. Thanks!

Larry
 
M

Matt Piazza, PMP

Matt S.,

Please provide us with more details so we too can find the answer.

Matt Piazza
 
A

Ahmad Khan

Hi,
I found the posting for Resource Usage view for a single project.
It is Dated: July 9 2004 20:01:52 PST
And the Subject line is : "Re: Resource Usage This Project Only"

Hope that helps!
Ahmad Khan
 
M

Matt Piazza, PMP

Admad,

Thanks.

Matt

Ahmad Khan said:
Hi,
I found the posting for Resource Usage view for a single project.
It is Dated: July 9 2004 20:01:52 PST
And the Subject line is : "Re: Resource Usage This Project Only"

Hope that helps!
Ahmad Khan
 
D

dwolf

I assume that you are talking about inserting a column for the "Project"
field in the Resource UsageView? If you then filter for the current project
name, you should see all of the tasks that the resources have for the
current project. All of the others just have the word "Piblished" in the
field.

--DWolf
 
Top