A
Arthur A
I have a series of tasks that are set with a FS relationship. There are no
lags. The early and late dates are consistant, but the total slack changes.
For example on one task the ES date is 4/7/10, the EF is 4/8/10, the LS is
2/12/10 and 2/13/10. The total slack is -61 days. OK, on a 7 day week it
doesn't equal 61 days. So that doesn't make sense to me. Next to this is
another task with an ES date of 4/4/10, an EF of 4/7/10, the LS is 2/10/10
and the LF is 2/12/10. The slack on that is -25 days. I don't understand.
Arthur A
lags. The early and late dates are consistant, but the total slack changes.
For example on one task the ES date is 4/7/10, the EF is 4/8/10, the LS is
2/12/10 and 2/13/10. The total slack is -61 days. OK, on a 7 day week it
doesn't equal 61 days. So that doesn't make sense to me. Next to this is
another task with an ES date of 4/4/10, an EF of 4/7/10, the LS is 2/10/10
and the LF is 2/12/10. The slack on that is -25 days. I don't understand.
Arthur A