meljay

Hi,

How do I do a snapshop (i.e. static master) of a Master project that's
already linked? I would really prefer not to have to insert all the projects
again without the links. Is there an easier way?

Thanks
 
J

JulieS

Hi Meljay,

Double click on the inserted project summary task for the linked project to
show the Inserted Project Information dialog box and on the Advanced tab,
uncheck link to project.
Unfortunately, you will need to repeat this for each inserted project in the
master.

Hope this helps. Let us know how you get along.

Julie
 
M

meljay

Hi Julie,
That seems to work. Since I have 10+ projects in the Master it's a tad
fiddly, but I think it will work.
Thanks,
meljay
 
M

meljay

Hi again Julie,
I just did as you suggested and it seemed to work. However I noticed the
total project % Complete changed very dramatically - went up nearly 15%!!
Do you know what's going on here?
meljay
 