Solution to MS Project truncating Notes field when Exporting?

J

John

CGallardo said:
Is there a Solution to not truncate the Notes field when Exporting MS Project?

CGallardo,
Yes. I assume you are doing a simple copy/paste or using an export map.
In either case the Notes will truncate either at the first line feed or
256 character limit. The way around this problem is either through VBA
or SQL. I have a couple of VBA macros that export the Notes (and a few
other fields) from Project to Excel. If you are interested, contact me
direct via e-mail.

Hope this helps.
John
Project MVP
 