Some tasks are missing in the PWA - PS2003

S

SS

Hi all,

Some users cannot find some of their assigned tasks in PWA. Most of the
tasks are displayed normally. Just a few of them are missing unexpectedly.

Any idea?
Thanks!
 
M

Marc Soester

SS that can have several reasons.
check the following
1. do your team members look in the timesheet under the linkg "current
tasks"? This means that some tasks that you are assigned to will not appear
if there are further then 2 weeks from the current date.

2. Have you used global resources? please check if you actually assinged
global resources to your tasks, not local resources.

3. have you publised the Project? the tasks that are missing, do they belong
to one project that has not been publised yet?

These are typically the most likely course of tasks not appearing
hope this helps
 
Top