Hi,

in the announcement of SP1 I understood that "My Tasks" gets a timesheet
like entry. After having applied SP1 to my system I still see the pop-up.

What am I missing?

Thanks
Adrian
 
M

Mike Mahoney

Hi,

in the announcement of SP1 I understood that "My Tasks" gets a timesheet
like entry. After having applied SP1 to my system I still see the pop-up.

What am I missing?

Thanks
Adrian

Adrian

You need to edit the webpart and select hours per day.

Mike
 
M

Mike Mahoney

Adrian

You need to edit the webpart and select hours per day.

Mike

Follow up:
On first investigation using this option in MY Task view seems a
little unreliable - in an example where I am assignment owner for
several resources and trying to update each, the entered data does not
always "stick", hitting recalculate may show previous values. Even
when it does stick, on saving or submittal I am getting a red message
- "Your updates were not saved because of the following reasons:" No
reason displayed but it seems that entered progress data gets lost.
Even if this does not appear there is a good chance that no updates
are available for approval. I have yet to test other update mechanisms

regards

Mike
 