Special Project Hours

B

bkoren

In general, I have my resources set up to work 8 hour weekdays. I
have a special project where my resources will work 11 hour days and
include Saturdays. With project server we have enterprise resources. Is
there a way to reflect this in MS Project 2007?

I appreciate any input.

Thanks,
Barb
 
S

Sandro Dadaczynski

you can give your tasks an 11 hour Calender (task information->
special->calendar). but then you must ignore the ressourcecalendar

sandro
 
Top