Scenario:
Particular project has multiple tasks that start and stop of different
days (nothing new). Some taks overlap (again, nothing new). Each task
requires x number of widgets to be in use so as to accomplish that
task. This information is recorded in a Number field. I would like to
display on the Gantt chart a total (for each day) of the number of
widgets in use. For example, Task 1 (2 widgets), Task 5 (15 widgets)
and task 9 (7 widgets) overlap so I would like to display a 24 at the
bottom of the chart on that day. Any ideas?
Many thanks.
Particular project has multiple tasks that start and stop of different
days (nothing new). Some taks overlap (again, nothing new). Each task
requires x number of widgets to be in use so as to accomplish that
task. This information is recorded in a Number field. I would like to
display on the Gantt chart a total (for each day) of the number of
widgets in use. For example, Task 1 (2 widgets), Task 5 (15 widgets)
and task 9 (7 widgets) overlap so I would like to display a 24 at the
bottom of the chart on that day. Any ideas?
Many thanks.