SPI /CPI values lost !!!!

R

Raj

I did another baselined to my project which was already
baselined before and published to the web now all the
baseline cost value is lost any idea as to why this
happned and how can we prevent this many thanks
 
R

RockNRoll

Have you tried Tools-Options-Calculations Tab, Earned Value button, then
under "Baseline for Earned Value calculations", then selecting your new
baseline?
 
R

Raj

Thanks for the help thi was very useful
-----Original Message-----
Have you tried Tools-Options-Calculations Tab, Earned Value button, then
under "Baseline for Earned Value calculations", then selecting your new
baseline?




.
 