J
Jimmy D
Hi,
Hope somebody can help me out (and I can explain what I want clearly):
We have a situation here where we have to do all test on 2 new equa
lines in our company. Line one has priority in starting up, but we hav
2 teams and we want team 1 who is cheking task 1 op CP1 to also do tas
1 on CP2.
I'll try to give an example
There are 2 computers (CP1 and CP2) and 2 working teams (Team 1 an
Team 2).
Team 1 starts Task1 on CP1 (eg 5 days)
Team 2 starts Task2 on CP2 (eg 10 days)
As soon as Team1/Task1 on CP1 is finished
Team 2 starts task2 on CP1 (eg 10 days) --> Task2 on CP2 is put o
hold
Team 1 starts task 3 on CP2 (eg 10 days)
As soon as Team2/Task2 on CP1 is finished
Team 1 starts Task 3 on CP1
Team 2 _resume_ with Task 2 on CP2 ermaining 5 days
So as you can see a certain task should be put on hold as long a
another hasn't finished, and then this task should be resumed.
Is something like this possible with MSP?
Thanks,
Jimm
Hope somebody can help me out (and I can explain what I want clearly):
We have a situation here where we have to do all test on 2 new equa
lines in our company. Line one has priority in starting up, but we hav
2 teams and we want team 1 who is cheking task 1 op CP1 to also do tas
1 on CP2.
I'll try to give an example
There are 2 computers (CP1 and CP2) and 2 working teams (Team 1 an
Team 2).
Team 1 starts Task1 on CP1 (eg 5 days)
Team 2 starts Task2 on CP2 (eg 10 days)
As soon as Team1/Task1 on CP1 is finished
Team 2 starts task2 on CP1 (eg 10 days) --> Task2 on CP2 is put o
hold
Team 1 starts task 3 on CP2 (eg 10 days)
As soon as Team2/Task2 on CP1 is finished
Team 1 starts Task 3 on CP1
Team 2 _resume_ with Task 2 on CP2 ermaining 5 days
So as you can see a certain task should be put on hold as long a
another hasn't finished, and then this task should be resumed.
Is something like this possible with MSP?
Thanks,
Jimm