Split timeline?

D

Dan

I have a project that last 12 months. There is a flurry of tasks in the first month, a flurry of tasks in the last month, and one long task for the 10 months in the middle. So I would like to hide those 10 months on my Gantt chart, just showing them as a break in the task bar and timeline.

Can it be done?
 
J

JackD

Sadly no.

-Jack

Dan said:
I have a project that last 12 months. There is a flurry of tasks in the
first month, a flurry of tasks in the last month, and one long task for the
10 months in the middle. So I would like to hide those 10 months on my
Gantt chart, just showing them as a break in the task bar and timeline.
 
J

John

Dan,
As far as a direct approach Jack is exactly right, but your scenario
requires some thinking outside the box. How about the following. Put the
first month's flurry of tasks in its own Project file, the 10 month slow
roll task in its own file and the last month's flurry in yet a third
file. External links can be used between files to maintain schedule
logic. You could also create a master file with all three inserted
subprojects however you will still face the timeline issue when viewing
the master. At least with three files, a timeline can be chosen that is
best suited for the ongoing activities.

An alternate off the wall approach might be to set up two custom views.
Once with a detail timescale for viewing tasks in the first and last
months and one with a gross timescale for viewing the 10 month period.

There are probably other ways to get there also. It depends on what you
want to see and do or should I say, what you are willing to see and do.

Just some thoughts, brought to you by the guy outside the box :)
John
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top