G
gzagrzebski
We want to have projects schedules and tasks created by a project
manager. This person would assign generic resources to the tasks. Then
a resorce manager (different person) would reassign the task to a live
resource. If the schedules change or other tasks are added this would
be done again by the project manager and then later reassigned by the
resource manager.
I assume this should be possible. If so, is there any security changes
required? Can two people change a schedule? Who does the updates when
tasks assignments are updated by resources? Anyone doing it this way?
Any problems?
manager. This person would assign generic resources to the tasks. Then
a resorce manager (different person) would reassign the task to a live
resource. If the schedules change or other tasks are added this would
be done again by the project manager and then later reassigned by the
resource manager.
I assume this should be possible. If so, is there any security changes
required? Can two people change a schedule? Who does the updates when
tasks assignments are updated by resources? Anyone doing it this way?
Any problems?