H
HT
This has to do with an overallocated resource. I thought I could split a
resource's work if a resource is overallocated with a task assignment. I
thought that if this task had more than one resource assigned, and one
resource is overallocated, that you could split the overallocated resources'
work without affecting the other resources assigned to the task. My
understanding is that this can be done in Resource Usage or Resource
Allocation view by selecting the Work cell where there is overallocation and
pressing Insert. It's supposed to delay the task out (e.g.) 1 day while
leaving the other resource assignments alone.
Only when I press Insert, nothing happens. I thought it was because Fixed
Duration was set, but I turned that off and it still didn't work. Does anyone
know what I am doing wrong?
Thanks -
HT
resource's work if a resource is overallocated with a task assignment. I
thought that if this task had more than one resource assigned, and one
resource is overallocated, that you could split the overallocated resources'
work without affecting the other resources assigned to the task. My
understanding is that this can be done in Resource Usage or Resource
Allocation view by selecting the Work cell where there is overallocation and
pressing Insert. It's supposed to delay the task out (e.g.) 1 day while
leaving the other resource assignments alone.
Only when I press Insert, nothing happens. I thought it was because Fixed
Duration was set, but I turned that off and it still didn't work. Does anyone
know what I am doing wrong?
Thanks -
HT