J
Jason-W
Hi,
I'm using MSP Server 2003 & MSP Pro2003. I'm trying to
get a view that shows a column/bar chart showing the
workload assigned to a single project broken up on a
weekly basis. Each bar should be divided up to show each
resource's contribution to that week's total workload. Is
there anyway to do this on either the Server or the
desktop software?
Thanks
--Jason
I'm using MSP Server 2003 & MSP Pro2003. I'm trying to
get a view that shows a column/bar chart showing the
workload assigned to a single project broken up on a
weekly basis. Each bar should be divided up to show each
resource's contribution to that week's total workload. Is
there anyway to do this on either the Server or the
desktop software?
Thanks
--Jason