Standard Calendar: Change working Time..

H

Haris

Hi,

By opening the Enterprise Global, we can use the "Change Working Time.."
feature under the "Tools" menu to mention any non-working days for the year.
But some of the resources for any critical projects within the organization
might have to be working on such days as well. What could be the possible
solution for such case? Is is possible to define calendars for each
project/group of projects? So that we can somehow allow the PMs to define
their own calendars/non-working days?
Looking forward.

Regards,
Haris
 
R

Reid McTaggart

You should learn about Task calendars. For a task that must be done
regardless of the day, you can use, for example, a 24/7 calendar and set it
to ignore the resources' calendars.
 
Top