Start and Finish in TimeSheet in Tasks

L

Leonard

Is there a way to make the Start and Finish Dates (or at least Start) fields
editable (read-write) in the Time Sheet View of Tasks in Project Web Access?
 
D

Dale Howard [MVP]

Leonard --

Team members cannot directly change the Start or Finish dates of any task
assignment. However, if you add the Actual Start and Actual Finish fields
to the list of Published Fields, users can modify these values on their
timesheets, which will indirectly impact the Start and Finish dates of the
tasks. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"


Leonard said:
Is there a way to make the Start and Finish Dates (or at least Start) fields
editable (read-write) in the Time Sheet View of Tasks in Project Web
Access?
 