R
Ripper
I have some fixed duration tasks that are being updated with effort. When
the first actuals are submitted, the start date changes to that date even if
the update is within the duration of the task. Example;
Task has a start of 10/1 and a 5 day duration with an end fo 10/5
Time is submitted for 10/3
Task start date moves to 10/3 and the end date pushes out.
Any way to keep the start date at 10/1?
the first actuals are submitted, the start date changes to that date even if
the update is within the duration of the task. Example;
Task has a start of 10/1 and a 5 day duration with an end fo 10/5
Time is submitted for 10/3
Task start date moves to 10/3 and the end date pushes out.
Any way to keep the start date at 10/1?