Why is the task start date with a predecessor task not the next working day?
So if task1 finishes on Thursday Jan. 22 and task2 has identified task1 as a
predecessor, the expectation is task2 would start on Friday Jan. 23 (the next
day)but task2 comes up to start on the same day as the end day of task1 (ie.
Thursday).
So if task1 finishes on Thursday Jan. 22 and task2 has identified task1 as a
predecessor, the expectation is task2 would start on Friday Jan. 23 (the next
day)but task2 comes up to start on the same day as the end day of task1 (ie.
Thursday).