Start, Finish and Duration Changes in MS Project 2003?

S

Shiva Chaitanya

Hi

We are using MS Project 2003.

I see the start, finish and duration in a project schedule changes with
respect to the project progress.

Why does this happen?

Thank you
Chaitanya.
 
J

Jan De Messemaeker

Hi,

When a task is done on an other time than the one scheduled, this must have
an influence on the tasks linked to it, so its start, finish and duration
have to adapt to reality.
If you want to keep track of the original schedule, you should save it as a
baseline (tools, tracking, save baseline) BEFORE starting tracking.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
Top