Sorry, I now see what actual duration is. In Primavera I
used to create formulas to create actual durations because
that program handles "duration" differently.
But that does not address the situation where when I
select Tools:Tracking

roject Update:Begin all remaining
work at [pick a date] all the other tasks except this one
has the remaining work moved to the begin at the date
selected but this one task still does not. Instead on this
task it spreads evenly across the task duration.
Thanks
Jim
-----Original Message-----
Hi Jim,
I don't understand! If the actual duration = the remaining
duration, then Project is corrent in stating it is 50% Complete.
what's the problem?
Mike Glen
MS Project MVP
.