Bruno, You can add a column for Variance Start or Variance Finish. MSP
calculates the current or actual dates from the baseline dates. You'll get a
positive or negative number. Not only can you see if you project is on track
but look at every task. You can filter on this also. Adding baseline bars to
the graphics is also helpfull. If you haven't set a baseline yet, I suggest
you do so ASAP.
Good Luck!!