Is there a way to have the notes from a task entered
automatically in a status reprot? We are using Project
2002 pro with project server. Thanks

Kan
 
D

Dale Howard [MVP]

Kan --

I do not believe there is any default method for automatically including
task notes in a Status Report in PWA. Although you can insert the task
names into the Status Report, I believe the only way you can insert task
notes is by using copy and paste. Sorry for the bad news.
 