Annemarie
Hi
I have set up a shared resource pool. the problem is that when people are
allocating resources to their individual projects they often mistype or make
up resource names when searching for resources. When they save their project
these invalid resources are added to the resource pool. How can I set up the
resource pool or individual projects so that resources can only be added or
amended in the resource pool not via individual projects. Of course I still
need to be able to update the resource pool with the allocations/dates/work
from the individual projects - just restrict the selection to only those
resources in the resource pool.
Any thoughts much appreciated.
Annemarie
I have set up a shared resource pool. the problem is that when people are
allocating resources to their individual projects they often mistype or make
up resource names when searching for resources. When they save their project
these invalid resources are added to the resource pool. How can I set up the
resource pool or individual projects so that resources can only be added or
amended in the resource pool not via individual projects. Of course I still
need to be able to update the resource pool with the allocations/dates/work
from the individual projects - just restrict the selection to only those
resources in the resource pool.
Any thoughts much appreciated.
Annemarie