Stoplights

B

BTOjohn

I'm probably being a bit dense here, but no-one can see me blush!

I've just followed the excellent instructions on project experts FAQs about
how to set up a stoplight indicator for schedule slippage, and it's worked a
treat.

I now want to set one up for work, to indicate when work is running out, but
there is no option for work in the Task Custom Enterprise Field. The options
appear to be Cost, Date, Duration, Flag, Number and Text - no Work!

Thanks in advance...

John
 
B

BTOjohn

OK, I was just being thick. I just select eg number, and then from the
formula menu insert the work field that I desire...at least I got there first
=/
 
Top