A
AndreSiregar 2002
I have a question on MS Project Server that I hope you can answer for
me. Here's the problem. Let's say I have a 2-day Fixed Duration task
whose baseline starts on Monday and ends on Tuesday. Then I go to PWA
to input the actual hours.
Now I input 8 hours on Wednesday (in other words, I only start the
task after it's supposed to be finished according to the baseline),
then have the task approved and updated. Upon approval, I will see
that the task now has a duration of 3 days. My % Complete is now at
33% (1 day / 3 days of duration).
Why has the duration changed? This is a Fixed Duration task.
Strangely, if the task's type had been Fixed Unit, the duration would
not have changed. Also, if I don't use PWA, but directly input the
Actual Work using Project Pro (8 hours on Wednesday), this strange
behaviour does not occur.
Thanks.
me. Here's the problem. Let's say I have a 2-day Fixed Duration task
whose baseline starts on Monday and ends on Tuesday. Then I go to PWA
to input the actual hours.
Now I input 8 hours on Wednesday (in other words, I only start the
task after it's supposed to be finished according to the baseline),
then have the task approved and updated. Upon approval, I will see
that the task now has a duration of 3 days. My % Complete is now at
33% (1 day / 3 days of duration).
Why has the duration changed? This is a Fixed Duration task.
Strangely, if the task's type had been Fixed Unit, the duration would
not have changed. Also, if I don't use PWA, but directly input the
Actual Work using Project Pro (8 hours on Wednesday), this strange
behaviour does not occur.
Thanks.