Sub task days not adding to total days of task

A

Ashley Matteson

I am having trouble with my tasks in a project adding in the total days from
their sub tasks.

An example would be: TASK A = 25 DAYS
SUBTASK A1 = 20 DAYS
SUBTASK A2 = 15 DAYS
SUBTASK A3 = 25 DAYS
TASK A should equal 60 Days but only equals 25. Any ideas on how to fix
this problem?

Please email the answers to [email protected] and post here.

THANK YOU!!!
 
J

Jonathan Yong

Did you indent all the subtask to be under Task A and specify the
predecessor relationship among the subtasks?

Also check you have auto calculate turn on.
 
Top