D
Dave
Hi,
My team creates projects initially with generic resources. As they project
progresses they'll want to substitute these resources with real team
members. We've worked out how to do it using Substitute resources but this
works on the entire project which is not a good thing for us. For example,
we may several deliverables assigned to an architect but we want to assign
the real architect for only one of these - the other deliverables are not
scheduled until later in the year.
How can I replace some tasks assigned to an architect to a real architect
but leave other generic architect's duties untouched?
Thanks
Dave
My team creates projects initially with generic resources. As they project
progresses they'll want to substitute these resources with real team
members. We've worked out how to do it using Substitute resources but this
works on the entire project which is not a good thing for us. For example,
we may several deliverables assigned to an architect but we want to assign
the real architect for only one of these - the other deliverables are not
scheduled until later in the year.
How can I replace some tasks assigned to an architect to a real architect
but leave other generic architect's duties untouched?
Thanks
Dave