A
Ashley Matteson
My subtask days are not adding to the total days of the project.
EXAMPLE: TASK A = 25 DAYS
SUBTASK A1 = 20 DAYS
SUBTASK A2 = 15 DAYS
SUBTASK A3 = 25 DAYS
TOTAL SHOULD = 60 DAYS BUT TASK A ONLY = 25
What can I do to fix this problem?
Please post here and if possible email me at [email protected]
EXAMPLE: TASK A = 25 DAYS
SUBTASK A1 = 20 DAYS
SUBTASK A2 = 15 DAYS
SUBTASK A3 = 25 DAYS
TOTAL SHOULD = 60 DAYS BUT TASK A ONLY = 25
What can I do to fix this problem?
Please post here and if possible email me at [email protected]