*Question about claiming status in the master, not the individual
files*: does this work with earned value? I have tried in the past to
update the status of the subproject from within the master project, but
the earned value data never accrues. If I however status update within
the subproject files, then open the master project file and change the
status date to that of what I updated to in the subprojects, then I find
the earned value gets updated.
Got any ideas what I'm doing wrong?
QUOTE=Jim Aksel;4624023]Things to check in the master
1. Tools/Options/Calculations (tab). Select "Inserted Project are
calculated like summary tasks."
2. Does the master have a baseline? That shouldn't matter if you are
using
ordinary %Complete. If you are using Physical%Complete post back as
the
story changes.
3. Consistent status dates in all the files including the master
(Project/Project Information... then set a status date).
4. Try claiming status from within the master, not the individual
files.
5. On Tools/Options/Calculation tab, is the calculation mode set to
automatic (in the master)?
If you need further help, please post back.
--
If this post was helpful, please consider rating it.
Jim Aksel, MVP
Check out my blog for more information:
http://www.msprojectblog.com
Les Bener said:
I have exact site project templates for 200 sites. The master schedule
contains the same template. I have created subprojects and inserted them
into the master schedule. % complete for subtasks transfers fine into the
master project within the inserted project, but I cannot get the percent
complete to rollup into the subtask in the Master Project Summary
template.