A
Ann
Is there a way to summarize the task for each resource on the resource usage
report a show a total by Outline level 1. I've got a plan with multiple
projects at the Outline Level 1 using a group of resources across projects.
I'd like to be able to see work by resource with task assigned to each
resource summarized up to the project (Outline Level 1) level underneath them.
report a show a total by Outline level 1. I've got a plan with multiple
projects at the Outline Level 1 using a group of resources across projects.
I'd like to be able to see work by resource with task assigned to each
resource summarized up to the project (Outline Level 1) level underneath them.