Summart tasks

P

Perl

Hello,

We have Project Server 2007.
Team member get tasks for "My tasks".
They see "Project name" and then "Tasks name",
they ask me to see summary tasks.
I know they can see it at the drill down but I want
to give them the option from the first screen.

Thanks

Perl
 
D

Dale Howard [MVP]

Perl --

At present there is no way to see the summary tasks on the My Tasks page. I
have absolutely no idea whether Microsoft intends to address this problem,
but I think they need to do so. For the moment, you will need to show your
TM's how to click the task name to see the summary tasks in the Assignment
Details view. Hope this helps.
 
V

Vadim Gerya, PMP

Unfortunately Dale is absolutely right :) !

In addition you may click at "Add Notes" on any task in My Task view. On the
top of popup window you will see "Task Path" with all summary tasks.
 
M

Mike Machulsky, President@Software Logic

this is a significant shortcoming; especially since summary tasks show in the
Project Server 2003 timesheet function.

has anyone come across a custom view to show the summary tasks?
 
D

Dale Howard [MVP]

Mike --

There's nothing available yet. Perhaps a talented software developer can
figure out a way around this problem.




"Mike Machulsky, President@Software Logic" <Mike Machulsky,
President@Software [email protected]> wrote in message
news:D[email protected]...
 