How can I show the progress of a summary task as a progress bar? I am able
to show a % complete but to view it graphically would help with presentations
when the sub tasks are hidden.

Thanks
 
R

Rod Gill

Hi,

Select Format, Bar Details and add a progress bar. You should be able to
work out what to do based on the other bars.
 