greensp
- Top Summary 83% 507d
- Project Release 83%
CC Completed 100% 1d
EC Completed 100% 1d
Code Complete 100% 1d
Internal Verification Start 100% 1d
Internal Verification Completed 100% 1d
First Customer Ship (FCS) Achieved 0% 1d
These are key milestones in our projects, If I change them to 0 Duration to become a milestone
the overall summary % changes to 0% completed .
I have marked these as Milestones under the Task Information and I had to change
all the Durations to 1 day to make the overall % work.
What is the recommended way to rollup these milestones?
- Project Release 83%
CC Completed 100% 1d
EC Completed 100% 1d
Code Complete 100% 1d
Internal Verification Start 100% 1d
Internal Verification Completed 100% 1d
First Customer Ship (FCS) Achieved 0% 1d
These are key milestones in our projects, If I change them to 0 Duration to become a milestone
the overall summary % changes to 0% completed .
I have marked these as Milestones under the Task Information and I had to change
all the Durations to 1 day to make the overall % work.
What is the recommended way to rollup these milestones?