Summary Task showing 99% Complete

S

ScottT

I'm not sure this question should be posted here, so please forgive if it's
mis-posted...

I have a summary task which has several summary tasks below it, each with
several leaf tasks below them. Every task and summary task is at 100%
complete, however, the summary task remains at 99%. Any thoughts on what I'm
missing?

Thanks much,
Scott
 
A

ad9aggie

Scott,

Do you have an ending milestone for your summary task that is not showing
100% complete? If you do, and it is not marked 100% complete, this is
probably why you are getting only 99% complete for that summary task.

Hope this helps,

Jonathan
 
S

ScottT

Thank you much for your reply... I didn't have a milestone, but I did notice
that one of the sub-tasks, though marked 100% complete, had a remaining time
of "0 days?". THough I'm not quite sure why a taks marked complete would
have an "estimated" 0 days to completion, when I changed that to "0 days",
the percentage of the summary task went to 100%.

Thanks again,
Scott
 