Hi,
What would be a best practice to use if my MSP schedule is broken down to
level of detail where I can not capture the actual cost and labor hrs. Same
time this level of details is critical to monitor the project progress. I
did assign resources to summary task but could not enter actual labor or cost
to the same summary task. I am working the idea to use Hammock task in
parallel to summary task. This way I think I could get the progress data from
the summary task and by loading hammock task with resources and actual I
could run EV and progress reports.
Any help or recommendations ???
Thanks,
Yakov
What would be a best practice to use if my MSP schedule is broken down to
level of detail where I can not capture the actual cost and labor hrs. Same
time this level of details is critical to monitor the project progress. I
did assign resources to summary task but could not enter actual labor or cost
to the same summary task. I am working the idea to use Hammock task in
parallel to summary task. This way I think I could get the progress data from
the summary task and by loading hammock task with resources and actual I
could run EV and progress reports.
Any help or recommendations ???
Thanks,
Yakov