Summary tasks double costs

N

Nikki

Hi,

I have entered the cost rate for each resouce into the resource sheet. In
my Cost table it calculates the cost per task depending on the cost rate for
the resoucre I have assigned. That is correct. But in my summary task line
it seems to double that cost. Can someone please tell me what I need to
change to fix this?

Thanks
 
J

Jan De Messemaeker

Hi Nikki,

You haven't also assigned the resources to the summary task have you?
 