In some of my projects I noticed strange behaviour:
times of subtasks don't equals the duration of main task. It can be seen on
PWA page and also in Project Pro.
For example:
subtask1 1 day
subtask 2 1 day
subtask 3 1 day
whole task 21 days !!!
So, 1+1+1=21 ?
regards
Mike