Steve Scott
Sorry this one won't go away...my colleagues are happy that the Summary = NO
criteria will mask out the errant summary tasks being displayed but why are
they being displayed? If I reschedule the entire project to start in 2008
and then run my elapsed tasks filter it still displays the summary tasks
which all start in 2008 - this seems impossible? I need to know why MS
Project is doing this, I can't keep using the phrase - don't worry "MS
Project is strange and does its own thing" for behaviour that can't be
explained.
Thanks in advance
Steve
criteria will mask out the errant summary tasks being displayed but why are
they being displayed? If I reschedule the entire project to start in 2008
and then run my elapsed tasks filter it still displays the summary tasks
which all start in 2008 - this seems impossible? I need to know why MS
Project is doing this, I can't keep using the phrase - don't worry "MS
Project is strange and does its own thing" for behaviour that can't be
explained.
Thanks in advance
Steve