Support resource

M

Marcus

In a number of areas, I have "support resources" (sort of
like Subject Matter Experts), that support a group of
tasks or project phase, giving say 20% of their time
throughout the lenght of that phase. The tasks, sub-
tasks, etc. within the phase change their actual start
dates and finish dates occasionally. Is there any way to
set a Start-to-start predecessor AND a Finish-to-finish,
so that the length (start and finish dates) of the
support task will last as long as the corresponding phase
lasts? Also, I need that person's time to be 20%
throughout on the support task. I appreciate any help
with this.

--Marcus
 
M

Mike Glen

Hi Marcus,

Welcome to this Microsoft Project newsgroup :)

A Hammock might be appropriate - please see FAQ Item: 19. Hammock Tasks

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on:)

Mike Glen
Project MVP
 
Top