NZ Projects

Yes. Data entered into timesheets can be imported into task updates and vica
versa.
 
D

Dale Howard [MVP]

Neal --

No. If your organization requires the entry of time spent on all types of
work, including both project and non-project work, then your resources my
use the My Timesheet page. To track task progress, your team members must
use the My Tasks page. As pointed out by NZ Projects, you import the data
entered in one into the other, but there is no SINGLE location in which to
do both. Hope this helps.
 
M

Michael Brown

Dale,

do you know if the Outlook Active-X control might do a better job of this? I
don't have it installed, but my understanding is that you can enter actual
hours (ala a timesheet) AND update remaining effort estimates all on the same
single page/process in Outlook?
 
D

Dale Howard [MVP]

Michael --

I don't think the Outlook add-in will be much help to you either.
Unfortunately, there is no single location in which to enter all types of
time, status tasks, AND adjust the Remaining Work on a task. Hope this
helps.
 