When processing timesheet updates in PWA, on clicking 'Update All', relevant
schedules are opened in MS Project and the changes are applied. What also
happens is that any pending task updates get automatically sent out (the same
effect as a 'Publish New and Changed Assignments'). Is there any way of
stopping these updates being auto-sent? What I'd like to do issue these
updates selectively (much as you can when choosing 'Publish New and Changed
etc'); not being able to, means a lot of unnecessary updates get sent to
resources - net result being they take less notice of them.
Any clues?
Thanks in advance.
Kev.
schedules are opened in MS Project and the changes are applied. What also
happens is that any pending task updates get automatically sent out (the same
effect as a 'Publish New and Changed Assignments'). Is there any way of
stopping these updates being auto-sent? What I'd like to do issue these
updates selectively (much as you can when choosing 'Publish New and Changed
etc'); not being able to, means a lot of unnecessary updates get sent to
resources - net result being they take less notice of them.
Any clues?
Thanks in advance.