J
J.Allman
Here's my info:
MS Project 2007
Statistics for the MS project in question:
Start date 3/15/09 of project
end date 12/9/09
status date: "NA"
baseline: 6/19/09
current date is today, 6/30/09
Problem:
I have created a schedule that has tasks as far back as 3/15/09. I then
baselined a week or so ago (6/19/09) and today have entered the first actual
work update against this schedule. However, my sv% column is still showing 0%
on ALL tasks whether the task be an a task that should have started and
finished before the current day, or whether the task shows it was started and
finished before the cuurent day, or whether the task shows it should have
started already and hasnt reached its finished date because it is beyond the
current date. I have every variety of task in this huge schedule but none of
them that should be showing a SV% are showing anything but 0%
Although I am not tracking cost I have entered an hourly rate for all the
resources assigned to the tasks in order to produce the data for EV.
My question:
What do I need to do to get SV% to calculate WITHOUT the MS project altering
any of my data in the schedule...i.e. start/finish dates, hours worked, etc.?
MS Project 2007
Statistics for the MS project in question:
Start date 3/15/09 of project
end date 12/9/09
status date: "NA"
baseline: 6/19/09
current date is today, 6/30/09
Problem:
I have created a schedule that has tasks as far back as 3/15/09. I then
baselined a week or so ago (6/19/09) and today have entered the first actual
work update against this schedule. However, my sv% column is still showing 0%
on ALL tasks whether the task be an a task that should have started and
finished before the current day, or whether the task shows it was started and
finished before the cuurent day, or whether the task shows it should have
started already and hasnt reached its finished date because it is beyond the
current date. I have every variety of task in this huge schedule but none of
them that should be showing a SV% are showing anything but 0%
Although I am not tracking cost I have entered an hourly rate for all the
resources assigned to the tasks in order to produce the data for EV.
My question:
What do I need to do to get SV% to calculate WITHOUT the MS project altering
any of my data in the schedule...i.e. start/finish dates, hours worked, etc.?