Chris Walsh
I am trying to update my project plan with actuals done before we rolled out Project Server but everytime i want to save it says that the project actuals are out of sync with Project Server and wants to sync them but only in 1 direction, the Project server direction, all information in the Project Plan gets overwritten.
I deleted the project from Project Server and tried importing the project as a new project with the actuals already included but it didn't like that either.
What can i do to keep the actuals??