Sync to Protected Actuals

S

Sally

Hiya
When updates are made from timesheets into plans, on
several occasions, actuals in the past are replaced with
zero hours for some resources. When we choose tools -
tracking - sync to protected actuals then teh hours do
come back, but my question is, is there a way to do this
automatically on save, or to stop it happening altogether?

Many thanks in advance

Sally
 