O
Oakwood Jay
We have been working with the OLAP cube functionality in Project 2007. We
learned that when you add or modify an issue (in the project workspace), you
then have to do one of two things: re-publish the project or synchronize the
project workspace with the Reporting Database in Project Server (from the
Server Settings area of PWA).
We don't want to force project managers to republish projects every day
(currently we build the OLAP cube every day), and manually synchronizing is
tedious. Has anyone run into this problem and worked out a programmatic
solution? One idea is to synchronize all project workspaces with Project
Server as part of the cube build, maybe using the Eventing service.
Thanks in advance!
learned that when you add or modify an issue (in the project workspace), you
then have to do one of two things: re-publish the project or synchronize the
project workspace with the Reporting Database in Project Server (from the
Server Settings area of PWA).
We don't want to force project managers to republish projects every day
(currently we build the OLAP cube every day), and manually synchronizing is
tedious. Has anyone run into this problem and worked out a programmatic
solution? One idea is to synchronize all project workspaces with Project
Server as part of the cube build, maybe using the Eventing service.
Thanks in advance!