Task Baselines

D

David

If a new project plan has been developed during the start of the project &
baselined. During the course of the project some tasks could be removed from
the project . Is it possible to keep track of all the deleted tasks baseline
information on the same plan? Does anyone have any suggestions to the above.
 
D

Dale Howard [MVP]

David --

Rather than removing the tasks, you should cancel the tasks by setting the
Remaining Work to 0 hours on each task. This way you will maintain the
Baseline information for each of the cancelled tasks. Beyond this, I would
also add a Note to each cancelled task documenting the reason for cancelling
the task. Hope this helps.
 