We are running Project Server 2003, using SharePoint. The problem that we
are having is that task changes are not appearing on the PMs 'Updates'
screen. Any task changes that are sent to any PM do accumulate (if a users
sends 2 tasks for approval, then later 1 task, it will show that 3 are
waiting approval), but if you ask to filter assignments that are waiting for
manager approval, it shows none, and if you look at the log of approved task
changes, it shows none (after a point in time; it used to work!).
Everything listed applies to all of our PMs.
Any ideas?
There are no related entries in the server event log.
Thanks in advance,
Michael
are having is that task changes are not appearing on the PMs 'Updates'
screen. Any task changes that are sent to any PM do accumulate (if a users
sends 2 tasks for approval, then later 1 task, it will show that 3 are
waiting approval), but if you ask to filter assignments that are waiting for
manager approval, it shows none, and if you look at the log of approved task
changes, it shows none (after a point in time; it used to work!).
Everything listed applies to all of our PMs.
Any ideas?
There are no related entries in the server event log.
Thanks in advance,
Michael