task change by PWA 2007

J

Jose X Perez

Hi everyone,
At my tasks, the team members can see and change starat, finish and %
complete.
How can I make that the users only can see those fields but just change %
complete.
I want to do this because my users can change the % complete but they should
not be able to change the schedule of the task.

Thank for your help.
Jose X Perez
 
P

Paul Conroy

There's no config/option that can help you here.

You've got two options,

User education and process or
Develop a custom web ui
 