J
Jose X Perez
Hi everyone,
At my tasks, the team members can see and change starat, finish and %
complete.
How can I make that the users only can see those fields but just change %
complete.
I want to do this because my users can change the % complete but they should
not be able to change the schedule of the task.
Thank for your help.
Jose X Perez
At my tasks, the team members can see and change starat, finish and %
complete.
How can I make that the users only can see those fields but just change %
complete.
I want to do this because my users can change the % complete but they should
not be able to change the schedule of the task.
Thank for your help.
Jose X Perez