task column display name

B

benc

Is there a way to change the display name of the task colum
in project view in PWA, eg., Text1 to Document Status
you can do this in Project, but does not seem to in PWA

benc
 
G

Gary Chefetz [MVP]

Benc:

There's no way to control it globally, but local fields that you customize
will show up in Project Server, however they'll contain the name given to
them by the last person who published a project.
 